The test run of PE600×900 jaw crusher is very important. Whether it is before purchase or after purchase and installation, users should pay attention to it. But what specific aspects need to be tested during the test run, and what details do we need t
The test run of PE600×900 jaw crusher is very important. Whether it is before purchase or after purchase and installation, users should pay attention to it. But what specific aspects need to be tested during the test run, and what details do we need to pay attention to?
1. Before the test run, check whether all solid parts are in good condition to ensure that there is no looseness;
2. Check the adjustment device of the discharge port of PE600×900 jaw crusher again. The adjustment standard should strictly follow the adjustment range specified in the manual;
3. During the test run, observe the operating status of the flywheel and groove wheel to ensure smooth operation;
4. Ensure that all friction parts are free of scratches, chips and grinding, and no abnormal noise. If any abnormality is found, stop the machine immediately for inspection and elimination;
5. After 2 hours of continuous operation, the bearing temperature rise shall not exceed 30℃.
Previous: SMP Crusher
Next: SMP Crusher
The test run of PE600×900 jaw crusher is very important. Whether it is before purchase or after purchase and installation, users should pay attention to it. But what specific aspects need to be tested during the test run, and what details do we need t
The test run of PE600×900 jaw crusher is very important. Whether it is before purchase or after purchase and installation, users should pay attention to it. But what specific aspects need to be tested during the test run, and what details do we need to pay attention to?
1. Before the test run, check whether all solid parts are in good condition to ensure that there is no looseness;
2. Check the adjustment device of the discharge port of PE600×900 jaw crusher again. The adjustment standard should strictly follow the adjustment range specified in the manual;
3. During the test run, observe the operating status of the flywheel and groove wheel to ensure smooth operation;
4. Ensure that all friction parts are free of scratches, chips and grinding, and no abnormal noise. If any abnormality is found, stop the machine immediately for inspection and elimination;
5. After 2 hours of continuous operation, the bearing temperature rise shall not exceed 30℃.